How Long a Custom Pool Takes in Western Washington

Updated: Nov 9
In the Pacific Northwest, people start thinking about a pool in May. The sun finally shows up, the kids are home and somebody says it at dinner: we should just do it.
By then, that summer is spoken for. From the first phone call to the first cannonball, plan on about eight months to a year in Pierce County and about a year in King County.
Here's where the time goes, and what you can do to keep it moving.
Stage one: the first visit
It starts with a call or a text to Julio. He'll come out, walk the yard and ask how your family spends a Saturday in August. He's looking at the things that shape everything later: how equipment gets into the backyard, how the ground slopes, where the big trees are, where the afternoon sun lands and what you see from the kitchen window.
We talk about budget at this visit too. Most of our custom pools start between $150,000 and $180,000, and rock work is on top of that. Putting the number on the table early saves everyone time.
Stage two: design
Rock pools get a clay model. Julio & Layne build your pool in miniature so the whole family can stand around it, see it from every side and change it. Move the waterfall. Make the cave taller. Add a slide because somebody under twelve made a very good argument.

Clean-line pools get a full 3D rendering instead, since tile, coping and straight edges read well on a screen.
Plan on a few rounds of changes. This is the cheapest place in the whole project to change your mind. Changing clay takes a thumb. Changing shotcrete takes a jackhammer.
Stage three: engineering and permits
Nobody gets excited about this part, so we handle it for you.
Every city and county in western Washington runs its own review. A pool needs engineering and a barrier plan. Depending on your lot, it may also need a closer look at soil, slopes, drainage or nearby wetlands and streams. In unincorporated King County, for example, a pool permit calls for a geotechnical evaluation or presumptive soil values. It also needs a barrier that meets code: at least 48 inches tall with self-closing, self-latching gates, or an approved alternative like a powered safety cover.
How long it takes depends on where you live. In Pierce County, permits are coming back in about three to four months. In King County, plan on six to eight.
Our team pulls the permits and handles the back and forth with the reviewers. The most useful thing you can do is answer questions quickly when they come in and get any HOA approval moving at the same time.
Stage four: construction
Once the permit is in hand, the build usually runs four to six months. When schedules line up, it can be closer to three.

Layne runs the job site. The order goes roughly like this:
Layout and excavation
The steel framework, with double rebar
Plumbing
Shotcrete
Rock carving and staining, or tile and coping
Decking and concrete
Plaster, water and startup
Rain is part of building here. Fresh shotcrete needs to be protected from rain until it sets, usually four or five hours according to the American Shotcrete Association. After that, rain helps it cure. We plan pours around the forecast and keep building through the wet months.

Stage five: first swim
We fill it, start it up and walk you through the equipment. Then it's yours.
What you can do while you wait
Pick a direction. Wild means carved rock, grottos and waterfalls. Minimal means clean lines, tile and coping. Plenty of yards end up with a little of both.
Save photos of pools you love and write down what you love about each one.
Decide early on the things that need pipes, wires or gas before the shotcrete goes in: a spa, fire features, lighting, an automatic cover.
Plan the rest of the backyard now, even if you build it later. Patios, walls and an outdoor kitchen are easier to lay out at first than work around later.
When to call
If you're picturing anytime between summer 2027 and 2028, now is a good time. Design and permits can run through the wet months, and construction lands when the weather is on your side.
The sooner you call, the sooner we can tell you whether your city's permit timeline makes your timeline goal possible.
Fiberglass is the one way to shorten the build. A fiberglass pool takes about six to eight weeks of construction once permits are approved. The permit wait is the same either way.
Call or text Julio at 425.336.9310, or request a consultation online.